The Pearl River Valley Water Supply District issued the following statement:
The temporary detour on Harbor Drive in Ridgeland will remain in place throughout the day.
Progress
on the 30" water main is progressing. The repair has been made to the
line and pressure testing is underway which is expected to take several
hours. Once the repair has passed testing, then the task of restoring
the road bed and road surface will begin. It is important to note this
repair had to be completed in a very deep trench, over ten feet
underground. Likewise, restoring the area will take some time to
complete.
Please reduce your speed and pay close attention to the temporary traffic control at the crossover locations.
1 comment:
Fear not. Rudy is the consulting engineer on the project.